Remodeling Bathrooms at a Barnes and Noble in Brandon, FL

Hybrid Construction was contracted to remodel both bathrooms at a Barnes and Noble bookstore in Brandon, FL. The store remained open during the course of the project so coordination with bath access was very important. The existing baths did not have proper ADA clearances at the entry door, so layout changes were necessary. Other Scope of work for the project included demolition, framing, drywall, paint, wall tile, floor tile, solid surface countertops, sinks, faucet, toilets, bath accessories, and new bathroom partitions. Close coordination between the service company and store manager was necessary to properly execute the work. The duration of this project was 4 weeks. (2 weeks per bath).